Water and waste metrics: calculating and steering them correctly

Guide ESG performance management: Environmental KPIs

How to calculate water withdrawal, discharge and consumption, waste volumes and recovery rates under ESRS E3, ESRS E5 and the voluntary standard, with examples.

easy4pro editorial team Last reviewed: 8 min read

Key takeaways

  • Water consumption is not water withdrawal: under ESRS E3, consumption = withdrawal − discharge, unless you measure or model it directly (AR 4). All water metrics are in cubic metres.
  • The revised ESRS ask for six water figures for own operations, including consumption in areas with water stress and water recycled, reused and stored (ESRS E3-4).
  • For waste, report total weight in its original state and the shares diverted from and directed to disposal, split into hazardous and non-hazardous and by operation type – plus the share whose destination is unknown (ESRS E5-5).
  • Energy recovery counts as “other recovery” only if it meets the R1 criterion of the Waste Framework Directive; otherwise it is incineration.
  • Intensity KPIs such as m³ per unit produced, tracked monthly, reveal leaks, mis-sorting and process changes long before the annual report.
Contents
  1. Water: the six figures
  2. Water in the voluntary standard
  3. Waste: amount and destination
  4. Waste in the voluntary standard
  5. Where the data comes from
  6. KPIs that steer
  7. Step by step
  8. Common mistakes
  9. How ECOMON helps you steer water and waste metrics
  10. Frequently asked questions

After energy and emissions, water and waste are the most common environmental metrics – and the ones most often mixed up. Withdrawal or consumption? Recovered or disposed of? Wet or dry weight? With the definitions of the revised ESRS and a clean data basis, both topics can be reported correctly and steered well.

This guide answers: Which water and waste figures do the revised ESRS and the voluntary standard (VS) ask for? How are they calculated? Where does the data come from? And which KPIs help you steer during the year?

Example (fictional)

For years an Austrian brewery reported the amount on its water bill as “water consumption”. For its sustainability statement it separates withdrawal, discharge and consumption: 52,000 m³ withdrawn from the public supply and its own well, 38,000 m³ discharged, 14,000 m³ consumed – mostly water that leaves the site in beer and spent grains or evaporates. The analysis also shows that about a quarter of the withdrawal goes straight to the sewer as rinse water. A rinse-water recovery system installed in March cuts withdrawal by around 12% at the same output.

Water: the six figures

The revised ESRS (Delegated Regulation (EU) 2026/1563) ask for six water metrics for your own operations, in cubic metres (ESRS E3-4, paragraph 16 and AR 5):

Metric Meaning Brewery example
Total water withdrawal Water taken in from public supply, groundwater, surface water or third parties 52,000 m³
Total water discharge Water returned to sewers, surface water or third parties 38,000 m³
Total water consumption Water that does not return: evaporated, in products, otherwise not discharged; C = W − D 14,000 m³
Consumption in areas with water stress The part of consumption at sites in areas with water stress 0 m³ (no stressed site)
Water recycled and reused Water used again on site, for example treated rinse water 2,500 m³
Water stored Water held in storage, for example tanks or reservoirs 0 m³

Consumption may be measured directly, modelled, estimated or calculated as withdrawal minus discharge (AR 4). Whichever you use, keep the method and stay consistent across years.

The brewery’s water balance: withdrawal by source, discharge by destination and the resulting consumption (fictional example).
The brewery’s water balance: withdrawal by source, discharge by destination and the resulting consumption (fictional example).

Areas with water stress. Whether a site lies in an area with water stress is decided by the indicators and thresholds in ESRS E3, AR 2, assessed at least at river-basin level – for example with the WRI Aqueduct Water Risk Atlas. The guide on water stress at your sites shows how to screen and document each site.

Water in the voluntary standard

The VS (Delegated Regulation (EU) 2026/1560) asks for less (B6, paragraphs 36–37):

  • total water withdrawal – the amount drawn into the boundaries of the organisation or facility;
  • water consumption (withdrawal minus discharge from production processes) only if you have production processes that consume significant amounts of water, such as drying, power production, manufacturing or irrigation – and, separately, the amount consumed at sites in areas with water stress.

Both are voluntary for undertakings with 10 employees or fewer.

Waste: amount and destination

Under ESRS E5-5, paragraph 16, you report on waste from your own operations:

  • a description of your waste streams – a name, for example from the European List of Waste, and the key materials, such as metals, plastics or biomass (AR 4);
  • the total weight of waste generated;
  • the share diverted from disposal, split into hazardous and non-hazardous and by preparation for reuse, recycling and other recovery operations;
  • the share directed to disposal, split into hazardous and non-hazardous and by incineration, landfill and other disposal operations;
  • the share whose final destination is unknown.

Paragraph 17 adds the total amount of radioactive waste, where you generate any.

Destination Amount Share
Preparation for reuse 50 t 4.0%
Recycling 800 t 64.0%
Other recovery (energy recovery meeting R1) 150 t 12.0%
Diverted from disposal 1,000 t 80.0%
Incineration 100 t 8.0%
Landfill 120 t 9.6%
Directed to disposal 220 t 17.6%
Destination unknown 30 t 2.4%
Total 1,250 t 100%
Waste by destination: 80% diverted from disposal, 17.6% to disposal and 2.4% with an unknown destination (fictional example).
Waste by destination: 80% diverted from disposal, 17.6% to disposal and 2.4% with an unknown destination (fictional example).

Three rules prevent the most common errors:

  • Original weight. Report waste in its original state – no “dry weight” or other recalculation (AR 5).
  • R1 decides. Incineration with energy recovery counts as “other recovery” only if the plant meets the R1 criterion in Annex II of the Waste Framework Directive; otherwise it is incineration under disposal (AR 6). Ask your contractor which code applies.
  • Hazardous follows waste law. Whether waste is hazardous follows its classification under waste legislation, not your own judgement.

Waste in the voluntary standard

Under B7 of the VS (paragraphs 38–39) you disclose whether and how you apply circular economy principles, the total weight of waste with a split into hazardous and non-hazardous, the share diverted to recycling or preparation for reuse and – in sectors with significant material flows such as manufacturing, construction or packaging – the annual mass flow of relevant materials. All are voluntary for undertakings with 10 employees or fewer.

Where the data comes from

  • Water: utility bills, your own meters at wells and discharge points, discharge permits and test reports, and the treatment plant’s invoices for wastewater volumes.
  • Waste: weighbridge tickets, consignment notes and monthly or annual reports from waste contractors. Agree that contractors deliver weight, waste code and treatment operation (R or D code) per waste stream – ideally monthly and as a file.

What this means for you: the cleanest improvement is often contractual. One clause asking your waste contractors for monthly weights with treatment codes, as a file, solves most data problems at once.

KPIs that steer

For internal steering, intensities work well because they separate efficiency from volume:

  • water withdrawal per unit produced – m³ per tonne, hectolitre or overnight stay;
  • waste per unit produced – kg per tonne or per piece;
  • recycling rate and share of mixed waste as indicators of sorting quality;
  • share of waste with unknown destination – a data-quality KPI that should fall towards zero.

Tracked monthly with target ranges, leaks, mis-sorting and unusual amounts show up early. The guide on steering ESG KPIs all year explains how to set up such KPIs.

Step by step

  1. Map the flows. For each site, all water sources and discharge points, and all waste streams with contractor and treatment.
  2. Close the balance. Withdrawal, discharge and consumption per site; check that they add up and explain differences.
  3. Screen for water stress. Classify each site and document the indicator and dataset.
  4. Fix the waste data. Weights in original state, waste codes, R and D codes, hazardous flags, unknown destinations.
  5. Build intensity KPIs. Per unit produced, monthly per site, with target ranges.
  6. Review quarterly. Act on deviations and record the actions for the disclosures on actions and targets.

Common mistakes

  • Reporting withdrawal as consumption – the most common water mistake.
  • Mixing volume and weight: waste in cubic metres from container sizes instead of tonnes from weighbridge tickets.
  • Counting all energy recovery as recovery: only R1 operations qualify.
  • Hiding unknown destinations: they must be shown as their own share.
  • Dry weight: waste is reported in its original state.
  • Forgetting small sites: warehouses and offices whose waste is collected by the municipality still belong in the total.

How ECOMON helps you steer water and waste metrics

ECOMON structures water and waste data the way the standards ask for it.

  • Metrics by stream: each water source, discharge point and waste stream is a metric; metric groups combine them by destination or treatment, and KPIs consolidate per site and for the group.
  • Intensity KPIs: water and waste per unit produced, with health targets and benchmarks such as the prior year.
  • Automated data intake: workflows import utility and contractor data from your existing tools and files, and AI extracts values from uploaded reports for review.
  • Values with evidence: weighbridge tickets, contractor reports and meter readings stay attached to each value.
  • Notifications and OKRs: alerts when a KPI leaves its range, and OKRs with owners and deadlines for reduction projects.

Contact us for a demo.

Frequently asked questions

What is the difference between water withdrawal and water consumption? Withdrawal is all water you take in. Consumption is the part that does not return – it evaporates, goes into products or is otherwise not discharged. Under ESRS E3, consumption = withdrawal − discharge, unless you measure or model it directly.

Which unit do the ESRS use for water? Cubic metres or multiples of them (ESRS E3, AR 5).

Does waste-to-energy count as recycling? No. It counts as “other recovery” only if the plant meets the R1 criterion of the Waste Framework Directive; otherwise it is incineration under disposal. It is never recycling.

What if a contractor cannot tell us where the waste went? Report that amount as waste with an unknown destination (ESRS E5-5, paragraph 16(e)) and work with the contractor to reduce it.

Do we report wet or dry weight? The weight in its original state, without recalculation (ESRS E5, AR 5).

Do small companies have to report water consumption under the VS? Only if they have production processes that consume significant amounts of water; total withdrawal is the basic figure. Both are voluntary for undertakings with 10 employees or fewer.

Sources and legal basis

  1. Commission Delegated Regulation (EU) 2026/1563 – revised ESRS (ESRS E3-4 Water metrics, ESRS E5-5 Resource outflows)
  2. Commission Delegated Regulation (EU) 2026/1560 – sustainability reporting standards for voluntary use (VS), disclosures B6 and B7
  3. Directive 2008/98/EC (Waste Framework Directive), Annexes I and II
  4. Commission Decision 2000/532/EC – European List of Waste
  5. World Resources Institute: Aqueduct Water Risk Atlas

Sources last checked on 20 November 2026.

This article is for general information only and does not replace legal, tax or audit advice.